10 Marla House Grey Structure Cost Estimation in Pakistan (September 2025)
The 10 Marla House Grey Structure Cost Estimation in Pakistan in September 2025 is one of the most searched topics among home builders this year. Construction costs have fluctuated due to cement, steel, and labour price hikes. Whether you’re planning a new home or analyzing Pakistan’s construction market, understanding grey structure cost helps you set a realistic budget and avoid financial surprises during building.
What Does Grey Structure Include?
In Pakistan’s construction market, the grey structure of a 10 Marla house means all basic structural work, foundation, slabs, beams, columns, walls, and roof, but it excludes finishing such as paint, tiles, woodwork, and fixtures.
Therefore, when estimating cost, focus on:
- Cement, sand, and crushed stone
- Steel reinforcement (Sarya)
- Bricks and blocks
- Plumbing and electrical rough-ins
- Labor for structure and roof casting
Related reading: Construction Cost per Square Foot in Pakistan 2025
10 Marla House Foundation Cost in September 2025.
| Materials | Quantity | Rates | Total cost |
| Bricks | 28000 Bricks | 17/brick | Rs. 476000 |
| Sand | 690 cubic feet | 65/cubic feet | Rs. 44800 |
| Crush | 580 cubic feet | 135/cubic feet | Rs. 78300 |
| Cement | 185 bags | 1360/bag | Rs. 251600 |
| Steel (Grade 60) | 560 kg | 242/kg | Rs. 135500 |
| Polithene Sheets | 2 rolls | 6000/roll | Rs. 12000 |
| Bending wire, Nails, Tools, etc | Rs. 10000 | Rs. 10000 | Rs. 10000 |
| Transportation | Rs. 20000 | Rs. 20000 | Rs. 20000 |
| Back-filling (ghasuu) | Rs. 135000 | Rs. 135000 | Rs. 135000 |
10 Marla House Foundation’s Materials cost: Rs. 1163000
Total Labor cost of 10 Marla house foundations: Rs. 232000
10 Marla House Ground Floor Cost:
Meanwhile, once the foundation work is completed, next we start the Ground floor brick work and other work mentioned in the list below:
| Materials | Quantity | Rates | Total cost |
| Bricks | 27500 Bricks | 17/brick | Rs. 467000 |
| Sand | 980 cubic feet | 65/cubic feet | Rs. 63700 |
| Crush | 1050 cubic feet | 135/cubic feet | Rs. 141700 |
| Cement | 242 bags | 1360/bag | Rs. 329000 |
| Steel (Grade 60) | 2400kg | 242/kg | Rs. 580800 |
| Chogath | 10 pcs | 8200/pc | Rs. 82000 |
| Safety grills | 246 sqft | 240/sqft | Rs. 59040 |
| Shuttering & steel binding work | 1650 sqft | 45/sqft | Rs. 75000 |
| Polithene Sheets | 2 rolls | 6000/roll | Rs. 12000 |
| Bending wire, Nails, Tools, etc | Rs. 20000 | Rs. 20000 | Rs. 20000 |
| Transportation | Rs. 35000 | Rs. 35000 | Rs. 35000 |
| Main Gate cost | Rs. 135000 | Rs. 135000 | Rs. 135000 |
10 Marla House Ground Floor Construction Cost: Rs. 2000240
Total Labor cost of 10 Marla house, Ground Floor Structure work: Rs. 393000
10 Marla House First Floor & Penthouse Construction Cost
In addition, once the Ground Floor work is completed, next we start the First floor & Penthouse brick work and other work mentioned in the list below:
| Materials | Quantity | Rates | Total cost |
| Bricks | 33000 Bricks | 17/brick | Rs. 561000 |
| Sand | 1350 cubic feet | 65/cubic feet | Rs. 87750 |
| Crush | 1050 cubic feet | 135/cubic feet | Rs. 141700 |
| Cement | 248 bags | 1360/bag | Rs. 337300 |
| Steel (Grade 60) | 2500 kg | 242/kg | Rs. 605000 |
| Chogath | 10 pcs | 8200/pc | Rs. 82000 |
| Safety grills | 165 sqft | 240/sqft | Rs. 40000 |
| Shuttering & steel binding work | 1800 sqft | 45/sqft | Rs. 81000 |
| Polithene Sheets | 2 rolls | 6000/roll | Rs. 12000 |
| Bending wire, Nails, Tools, etc | Rs. 20000 | Rs. 20000 | Rs. 20000 |
| Transportation | Rs. 40000 | Rs. 40000 | Rs. 40000 |
10 Marla House First Floor & Mumty Construction Cost: Rs. 2007500
Total Labor cost of a 10 Marla house, First Floor & Penthouse Structure work: Rs. 370000
10 Marla house Plumbing work cost:
Meanwhile, once we complete the Structural work, next we start the MEP work, like Plumbing and electrical piping work, which is necessary in the grey structure work.
| Hot & cold water piping materials cost | Rs. 108000 |
| Drainage system piping materials | Rs. 118000 |
| Gas piping materials | Rs. 52000 |
| Water pump bore, and pump | Rs. 135000 |
| Labor cost for Plumbing work | Rs. 155000 |
10 Marla House Plumbing work Total Cost: Rs. 568000
10 Marla House Electricity work cost in Grey Structure:
| Piping materials and fittings (grey structure) | Rs. 124000 |
| Labor cost for Electricity work | Rs. 76000 |
10 Marla House Electric work cost: Rs. 200000
10 Marla House Plaster work cost:
In addition, once the Structural & MEP work is completed, next we start the inside and outside plaster work mentioned in the list below:
| Materials | Quantity | Rates | Total cost |
| Cement (inside and outside plaster work) | 235 Bags | 1400/bags | Rs. 329000 |
| Sand | 1680 cubic feet | 70/cubic feet | Rs. 117600 |
| Labor cost for a 10 marla house, plaster work | 3450 sqft | 125/sqft | Rs. 431300 |
10 Marla House Plaster work Total Cost: Rs. 877300
10 Marla House Grey Structure Total Cost:
10 Marla House Grey Structure Materials Total Cost: Rs. 5860000
10 Marla House Grey Structure total Labor Cost: Rs. 1658000
10 Marla House Grey Structure Total Construction Cost: 7600000
10 Marla House Construction cost PDF:
Powered By EmbedPress
Expert Opinion:
Overall, the 10 Marla House Grey Structure Cost Estimation in Pakistan (September 2025) ranges between PKR 7.5 million and PKR 9.5 million, depending on quality and location.
Moreover, using 60-grade steel, premium cement, and proper site supervision ensures structural durability.
On the other hand, cutting corners in grey work leads to long-term maintenance issues.
As a professional construction market analyst, I recommend setting aside an extra 5–10 % contingency budget to cover inflation and unforeseen structural needs. Whether you’re constructing in Lahore, Islamabad, or Karachi, careful material selection and labor management will define your project’s success.
Also read this: